October 2026 Update

Progress to Date:  Crews have finished realigning and patching 37th Avenue East at Crescent Ridge Road and opened both entrances to The Knoll. Crews have placed concrete for curb and gutter at the Arcadia Drive realignment. Curb, gutter and sidewalk have been placed along University Boulevard East from Windsor Drive to the former Jim Meyers Property.…

Read article
October 2, 2026 Roads Update

Progress: Crews have finished moving dirt and preparing the area between 4th Street and the Goodrich Spur railroad on Martin Luther King Jr. Boulevard. Office trailers and construction equipment are now in place on-site.  Next Steps: Crews will begin driving piles. This work is expected to continue through the end of October.  Pending railroad review…

Read article
September 2026 Update

Progress to Date:  Crews have installed new storm drains throughout the Redmont Drive, Arcadia Drive and Crescent Ridge Road areas. Landscaping crews have begun constructing a new retaining wall on the south side of University Boulevard East and have added trees, shrubs and sod along the corridor. Workers have built a new turn lane from University Boulevard East onto Crescent…

Read article
September 4, 2026 Update

Progress:Phases 1 – 8 work areas are substantially complete. All roads and sidewalks are now open. Next Steps: Final landscaping work and signage installation. Utility and roadway work at the intersection of Greensboro Avenue and 7th Street will occur between Tuesday, September 8, 2026 and Saturday, September 12, 2026. Upcoming Impacts: 7th Street, from Lurleen…

Read article
August 28, 2026 Update

Progress:Phases 1 – 6 work areas are substantially complete. Utility work in the Phase 7 and Phase 8 work areas is substantially complete. Next Steps: Landscaping work and signage installation continues. Sidewalk work in the Phase 7 and Phase 8 work areas is nearing completion. Bay parking work in the Phase 7 and Phase 8…

Read article