Progress:
Crews have finished moving dirt and preparing the area between 4th Street and the Goodrich Spur railroad on Martin Luther King Jr. Boulevard. Office trailers and construction equipment are now in place on-site.
Next Steps:
- Crews will begin driving piles. This work is expected to continue through the end of October.
- Pending railroad review and approval, residents will continue to see bridge-related activity, including construction of the temporary jump span bridges over the railroad mainline.
- Sanitary sewer construction will begin.
Upcoming impacts:
- Nearby residents may experience occasional construction-related noise.
- Martin Luther King Jr. Boulevard north of Fifth Street and Jack Warner Parkway west of Nick’s Kids Avenue will remain closed.