June 1, 2024

Progress All of the blasting for this project has been completed, and material haul-off is progressing on schedule. Waterlines were installed in April, and the lines on McWright’s Ferry Road have been switched over to the new feeds. Sanitary sewer line installation is in progress as of early June.  On the SR-297 (Bryant Bridge) side of…

Read article
May 1, 2024 

Progress Grading is almost complete! Only three areas of earthwork involving blasting and mass hauling remain. In April, the focus shifted to complete installation of around 3,800 feet of waterline on McWright’s Ferry Road. An additional crew was assigned to this effort, taking the completion time from the projection of a couple of months down…

Read article
April 1, 2024

Progress Drilling, blasting, and excavation continue to be the primary focus of the project. The contractor is nearing the end of the large-scale earthmoving, and the majority of the rock has been moved. The roadway is on grade between SR-297 (Bryant Bridge) and North River. Grading and earthwork south of SR-297 are progressing as well. The new…

Read article
March 4, 2024 

Progress Work continues on each side of SR-297 (Bryant Bridge). A significant percent of the earthwork leading to North River is complete, and the right of way is beginning to take shape between SR-297 and Rice Mine Road. East of North River, preparations are underway for final grading between North River and Oak Glen. All girders on both…

Read article
February 5, 2024

Progress Work has begun south of SR-297 (Bryant Bridge) and continues between SR-297 and North River. A substantial portion of the cut and fill is complete on the new portion of the road between North River and Oak Glen. Construction is in process of the roadway bridge over North River, and the truss span of the…

Read article
January 11, 2024

Progress The contractor has moved 60% of the required material on the project, installed girders on 3 of the 7 spans for the vehicle bridge, and laid asphalt on around 2000 feet of new roadway.  Currently, blasting and earthwork continues between SR-297 and North River and in the new section of the roadway south of…

Read article