October 2026 Update
Progress to Date: Work on installing foundation piles for the temporary bridge sections began on October 1, with several test piles completed to confirm installation requirements. Crews have continued pile installation for six support structures on the Mainline bridge and five support structures on the Goodrich Spur bridge. On the Mainline bridge, crews are now…
Read article