Posts

You are here:
August 25, 2026 Update

Progress:Following the groundbreaking, crews continued clearing dirt and old construction debris to prepare the site for the next phase of work. Additional equipment and crane mats were delivered, and a camera was installed near the MLK tie-in to support site safety and surveillance. The final plan for the temporary jump span has been submitted. The railroad will complete…

Read article
August 21, 2026 Update

Progress:Phases 1 – 6 work areas are substantially complete. Utility work in the Phase 7 and Phase 8 work areas is substantially complete. Next Steps: Sidewalk, bay parking and roadway work in the Phase 7 and Phase 8 work areas will continue. Landscaping work on the east side of Greensboro Avenue is scheduled to begin…

Read article
August 14, 2026 Update

Progress: Phase 1, Phase 2, Phase 3, Phase 4, Phase 5 and Phase 6 work areas are substantially complete. The southbound lane, sidewalk and adjacent bay parking of Greensboro Avenue in the Phase 5 and Phase 6 work areas was reopened on Monday, August 10. Storm drainage in the Phase 7 and Phase 8 work areas…

Read article
August 2026 Update

Progress to Date: Crews have made steady progress upgrading utilities and preparing the corridor for upcoming construction phases. The new 12-inch water main is fully installed along with connections to the existing system. Electrical teams continued placing underground conduit, light pole bases, in-ground boxes and fiberglass equipment bases along the south side of University Boulevard…

Read article
August 7, 2026 Update

Progress:Phase 1, Phase 2, Phase 3 and Phase 4 work areas are substantially complete. Demolition and utility work in the Phase 5 and Phase 6 work areas are complete. Sidewalk and roadway work in the Phase 5 and Phase 6 areas are nearing completion.  Next Steps: The southbound lanes, sidewalk, and adjacent bay parking of Greensboro Avenue in…

Read article
July 31, 2026 Update

Progress:Phase 1, Phase 2, Phase 3 and Phase 4 work areas are substantially complete. Demolition in the Phase 5 and Phase 6 work areas are complete. Utility work in the Phase 5 and Phase 6 work areas are nearing completion. New sidewalks in the Phase 5 and Phase 6 areas are complete from Babe’s Doughnuts to Chuck’s. The Greensboro…

Read article