May 22, 2026 Update
Progress: The Phase 1 work area is nearly complete, with bay parking as the final item. Phase 2 is nearing completion, with demolition and storm drainage work wrapping up. Gas relocation efforts are also nearing completion in the Phase 3 and Phase 4 works areas. Next Steps: Upcoming impacts: Pedestrian and local business access will…
Read articleMay 2026 Update
Progress to date: Over the past month, crews have made significant progress in preparing the ground and installing new curbs, gutters, sidewalks, and shared-use paths. Storm drains, sanitary sewer lines, and water lines have been added to modernize aging infrastructure. Work is also underway on the new north retaining wall, including excavation, placement of base layers,…
Read articleMay 15, 2026 Update
Progress: The Phase 1 work area is nearing interim completion. Gas relocation has been completed in the Phase 1 and Phase 2 work areas and has begun in the Phase 3 and Phase 4 work areas. Next Steps: Upcoming impacts: Pedestrian and local business access will remain open during the duration of the project. For…
Read articleMay 8, 2026 Update
Progress: Construction began on Monday May 4. Traffic control, wayfinding signage, and construction fencing was installed. Demolition began in the Phase 1 work area, along with storm drainage, concrete curb, gutter and sidewalk installation. Spire has begun gas relocation. Next Steps: In the Phase 1 work area storm drainage, concrete curb, gutter and sidewalk/bay parking…
Read articleMay 1, 2026 Update
Progress: The Greensboro Avenue Streetscape Project will begin on May 4, 2026. Pedestrian and local business access will remain open during the duration of the project. Upcoming Impacts: Beginning May 4: To receive email updates visit tuscaloosaroads.com/greensboro.
Read articleGreensboro Streetscape Project Construction Begins Next Week
On Monday, May 4, construction will start on Greensboro Avenue between University Boulevard and 7th Street, with work expected to be completed by the first home football game. This $4.3 million Elevate Tuscaloosa project is intended to strengthen pedestrian access and safety in our downtown area with wider sidewalks, landscaping, and safety improvements. Throughout the construction process,…
Read article