August 1, 2024
Progress Progress continues on the new portion of McWright’s Ferry Road with the placement of topsoil, grass, and stone base and pavement. Sanitary sewer installation on McWright’s Ferry Road has been completed from near North River to New Watermelon Road including the recently completed line across McWright’s Ferry Road to Oak Chase. At the SR-297 (Bryant Bridge)…
Read articleJuly 1, 2024
Progress Primary areas of material haul-off have been completed, and only minor grading work remains on the project. Grading work has begun to widen McWright’s Ferry Road, and fill material is visible on the east side of McWright’s in preparation for new curb and gutter. Sanitary sewer installation has progressed from south of Oak Glen to north…
Read articleJune 1, 2024
Progress All of the blasting for this project has been completed, and material haul-off is progressing on schedule. Waterlines were installed in April, and the lines on McWright’s Ferry Road have been switched over to the new feeds. Sanitary sewer line installation is in progress as of early June. On the SR-297 (Bryant Bridge) side of…
Read articleMay 1, 2024
Progress Grading is almost complete! Only three areas of earthwork involving blasting and mass hauling remain. In April, the focus shifted to complete installation of around 3,800 feet of waterline on McWright’s Ferry Road. An additional crew was assigned to this effort, taking the completion time from the projection of a couple of months down…
Read articleApril 1, 2024
Progress Drilling, blasting, and excavation continue to be the primary focus of the project. The contractor is nearing the end of the large-scale earthmoving, and the majority of the rock has been moved. The roadway is on grade between SR-297 (Bryant Bridge) and North River. Grading and earthwork south of SR-297 are progressing as well. The new…
Read articleMarch 4, 2024
Progress Work continues on each side of SR-297 (Bryant Bridge). A significant percent of the earthwork leading to North River is complete, and the right of way is beginning to take shape between SR-297 and Rice Mine Road. East of North River, preparations are underway for final grading between North River and Oak Glen. All girders on both…