May 8, 2026 Update
Progress: Construction began on Monday May 4. Traffic control, wayfinding signage, and construction fencing was installed. Demolition began in the Phase 1 work area, along with storm drainage, concrete curb, gutter and sidewalk installation. Spire has begun gas relocation. Next Steps: In the Phase 1 work area storm drainage, concrete curb, gutter and sidewalk/bay parking…
Read articleMay 1, 2026 Update
Progress: The Greensboro Avenue Streetscape Project will begin on May 4, 2026. Pedestrian and local business access will remain open during the duration of the project. Upcoming Impacts: Beginning May 4: To receive email updates visit tuscaloosaroads.com/greensboro.
Read articleGreensboro Streetscape Project Construction Begins Next Week
On Monday, May 4, construction will start on Greensboro Avenue between University Boulevard and 7th Street, with work expected to be completed by the first home football game. This $4.3 million Elevate Tuscaloosa project is intended to strengthen pedestrian access and safety in our downtown area with wider sidewalks, landscaping, and safety improvements. Throughout the construction process,…
Read articleApril 2026 Update
Progress to date: Over the past month, crews continued installing sewer and storm water drains and pipes along the northern sections. Additionally, utility crews continued to install gas and relocating transmission poles. Over the Spring Break closure, the underground work that crosses University Boulevard East was completed. Next Steps: Upcoming Impacts: To receive text updates for…
Read articleMarch 2026 Update
Progress: This month, crews continued installing sanitary sewer lines and storm drains in multiple locations. Utility teams also began to install gas service lines and duct banks, while progress was completed on a manhole installation. Next Steps: Upcoming Impacts: To receive text updates for traffic impacts, text UNIVBLVD to 888777.
Read articleFebruary 2026 Update
Progress: Stage 1 of construction began with new traffic patterns, lane, and road closures between 30th Avenue East and 34th Avenue. The site of a future drainage basin east of Windsor Drive has been mobilized and cleared. With the coordination of private utility companies, existing locations have been marked and utility work (including sewer, gas service lines,…
Read article