Greensboro Ave

You are here:
July 10, 2026 Update

Progress: The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Gas relocation is also complete. Demolition, sidewalk construction and utility work in the Phase 3 and Phase 4 areas…

Read article
July 2, 2026 Update

Progress: The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Gas relocation is also complete. Sidewalk construction between Swag and the former Downtown Trading Company is…

Read article
June 26, 2026 Update

Progress:  The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. In Phase 3, significant progress has been made with curb and sidewalk completion. Gas…

Read article
June 18, 2026 Update

Progress:  The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Next Steps:  Upcoming impacts:  Pedestrian and local business access will remain open during the…

Read article
June 12, 2026 Update

Progress:  The Phase 1 and Phase 2 work areas have reached substantial completion. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Next Steps:  Upcoming impacts:  Pedestrian and local business access will remain open during…

Read article
Streetscape
June 5, 2026 Update

Progress:  The Phase 1 and Phase 2 work areas have reached substantial completion, with new sidewalks and bay parking now in place. Expect the northbound lane of Greensboro Avenue, the adjacent bay parking, and the sidewalk between Gary Fitts Street and University Boulevard to reopen by Saturday, June 6. In Phase 2, demolition and storm drainage…

Read article
May 22, 2026 Update

Progress:  The Phase 1 work area is nearly complete, with bay parking as the final item. Phase 2 is nearing completion, with demolition and storm drainage work wrapping up. Gas relocation efforts are also nearing completion in the Phase 3 and Phase 4 works areas. Next Steps:  Upcoming impacts:  Pedestrian and local business access will…

Read article
Greensboro Avenue Streetscape Update
May 15, 2026 Update

Progress:  The Phase 1 work area is nearing interim completion. Gas relocation has been completed in the Phase 1 and Phase 2 work areas and has begun in the Phase 3 and Phase 4 work areas. Next Steps:  Upcoming impacts:  Pedestrian and local business access will remain open during the duration of the project. For…

Read article
Greensboro Streetscape Contruction
May 8, 2026 Update

Progress: Construction began on Monday May 4. Traffic control, wayfinding signage, and construction fencing was installed.  Demolition began in the Phase 1 work area, along with storm drainage, concrete curb, gutter and sidewalk installation. Spire has begun gas relocation. Next Steps: In the Phase 1 work area storm drainage, concrete curb, gutter and sidewalk/bay parking…

Read article