Greensboro Ave

You are here:
August 28, 2026 Update

Progress:Phases 1 – 6 work areas are substantially complete. Utility work in the Phase 7 and Phase 8 work areas is substantially complete. Next Steps:Landscaping work and signage installation continues.Sidewalk work in the Phase 7 and Phase 8 work areas is nearing completion.Bay parking work in the Phase 7 and Phase 8 work areas will…

Read article
August 21, 2026 Update

Progress:Phases 1 – 6 work areas are substantially complete. Utility work in the Phase 7 and Phase 8 work areas is substantially complete. Next Steps:Sidewalk, bay parking and roadway work in the Phase 7 and Phase 8 work areas will continue. Landscaping work on the east side of Greensboro Avenue is scheduled to begin during the week…

Read article
August 14, 2026 Update

Progress: Phase 1, Phase 2, Phase 3, Phase 4, Phase 5 and Phase 6 work areas are substantially complete. The southbound lane, sidewalk and adjacent bay parking of Greensboro Avenue in the Phase 5 and Phase 6 work areas was reopened on Monday, August 10. Storm drainage in the Phase 7 and Phase 8 work areas…

Read article
August 7, 2026 Update

Progress:Phase 1, Phase 2, Phase 3 and Phase 4 work areas are substantially complete. Demolition and utility work in the Phase 5 and Phase 6 work areas are complete. Sidewalk and roadway work in the Phase 5 and Phase 6 areas are nearing completion.  Next Steps:The southbound lanes, sidewalk, and adjacent bay parking of Greensboro Avenue in the…

Read article
July 31, 2026 Update

Progress:Phase 1, Phase 2, Phase 3 and Phase 4 work areas are substantially complete. Demolition in the Phase 5 and Phase 6 work areas are complete. Utility work in the Phase 5 and Phase 6 work areas are nearing completion. New sidewalks in the Phase 5 and Phase 6 areas are complete from Babe’s Doughnuts to Chuck’s. The Greensboro…

Read article
July 24, 2026 Update

Progress:Phase 1, Phase 2, Phase 3 and Phase 4 work areas are substantially complete. Demolition in the Phase 5 and Phase 6 work areas is nearing completion. Concrete and utility work in the Phase 5 and Phase 6 work areas are underway, with utility work expected to be complete by the end of the week.  Next Steps:Work in…

Read article
July 17, 2026 Update

Progress:The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Gas relocation is also complete. Demolition, sidewalk construction, bay parking and utility work in the Phase 3 and…

Read article
July 10, 2026 Update

Progress: The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Gas relocation is also complete. Demolition, sidewalk construction and utility work in the Phase 3 and Phase 4 areas…

Read article
July 2, 2026 Update

Progress: The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Gas relocation is also complete. Sidewalk construction between Swag and the former Downtown Trading Company is…

Read article
June 26, 2026 Update

Progress:  The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. In Phase 3, significant progress has been made with curb and sidewalk completion. Gas…

Read article