Weekly Update May 22nd

Progress:  The Phase 1 work area is nearly complete, with bay parking as the final item. Phase 2 is nearing completion, with demolition and storm drainage work wrapping up. Gas relocation efforts are also nearing completion in the Phase 3 and Phase 4 works areas. Next Steps:  Upcoming impacts:  Pedestrian and local business access will…

Read article
Greensboro Avenue Streetscape Update
Weekly Update May 15th

Progress:  The Phase 1 work area is nearing interim completion. Gas relocation has been completed in the Phase 1 and Phase 2 work areas and has begun in the Phase 3 and Phase 4 work areas. Next Steps:  Upcoming impacts:  Pedestrian and local business access will remain open during the duration of the project. For…

Read article
Greensboro Streetscape Contruction
Weekly Update May 8th

Progress: Construction began on Monday May 4. Traffic control, wayfinding signage, and construction fencing was installed.  Demolition began in the Phase 1 work area, along with storm drainage, concrete curb, gutter and sidewalk installation. Spire has begun gas relocation. Next Steps: In the Phase 1 work area storm drainage, concrete curb, gutter and sidewalk/bay parking…

Read article
Greensboro Avenue Streetscape
Greensboro Streetscape Project Construction Begins Next Week

On Monday, May 4, construction will start on Greensboro Avenue between University Boulevard and 7th Street, with work expected to be completed by the first home football game. This $4.3 million Elevate Tuscaloosa project is intended to strengthen pedestrian access and safety in our downtown area with wider sidewalks, landscaping, and safety improvements. Throughout the construction process,…