August 28, 2026 Update
Progress:Phases 1 – 6 work areas are substantially complete. Utility work in the Phase 7 and Phase 8 work areas is substantially complete. Next Steps:Landscaping work and signage installation continues.Sidewalk work in the Phase 7 and Phase 8 work areas is nearing completion.Bay parking work in the Phase 7 and Phase 8 work areas will…
Read article
