City of Tuscaloosa Holds Martin Luther King Jr. Boulevard/Jack Warner Parkway Improvements Groundbreaking

Tuscaloosa, AL – The City of Tuscaloosa held a groundbreaking ceremony for the Martin Luther King Jr. Boulevard/Jack Warner Parkway Improvements on Tuesday, July 14, at 8:15 a.m. Tuscaloosa Mayor Walt Maddox, District 1 Councilor Joe Eatmon and Alabama State Representative Chris England spoke during the ceremony. “One of the things I’m most proud of…

Read article
July 10, 2026 Update

Progress: The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Gas relocation is also complete. Demolition, sidewalk construction and utility work in the Phase 3 and Phase 4 areas…

Read article
MAYOR’S MINUTE – July 2, 2026

https://vimeo.com/1206276180?share=copy&fl=sv&fe=ci University Boulevard East At the beginning of the year, we broke ground on the University Boulevard East Improvement Project. This Elevate Tuscaloosa project, in partnership with Tuscaloosa Area Metropolitan Planning Organization, will make Alberta safer and more accessible.Over the past few months, our crews have made outstanding progress and I’m excited to share some…

Read article
July 2, 2026 Update

Progress: The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Gas relocation is also complete. Sidewalk construction between Swag and the former Downtown Trading Company is…

Read article