September 2026 Update

Progress to Date:  Crews have installed new storm drains throughout the Redmont Drive, Arcadia Drive and Crescent Ridge Road areas. Landscaping crews have begun constructing a new retaining wall on the south side of University Boulevard East and have added trees, shrubs and sod along the corridor. Workers have built a new turn lane from University Boulevard East onto Crescent…