August 25, 2026 Update

Progress:
Following the groundbreaking, crews continued clearing dirt and old construction debris to prepare the site for the next phase of work. Additional equipment and crane mats were delivered, and a camera was installed near the MLK tie-in to support site safety and surveillance. The final plan for the temporary jump span has been submitted. The railroad will complete its review before granting approval and allowing bridge construction to begin. Crews also received sanitary and storm drain pipes along with other related materials, which have been staged on-site.

Next Steps:
Continue shaping and leveling the ground along MLK between 4th Street and the railroad tracksBegin drilling beneath the railroad tracks to install a protective casing for the new sewer line Receive materials and start constructing the temporary support spans for the railroad's main track bridge.