Progress to date:
Over the past month, crews continued installing sewer and storm water drains and pipes along the northern sections. Additionally, utility crews continued to install gas and relocating transmission poles. Over the Spring Break closure, the underground work that crosses University Boulevard East was completed.
Next Steps:
- Continue installation of sanitary sewer, storm water drainage structures, piping and utility work along the north side of University Boulevard East
- Relocation of gas main, followed by system testing
Upcoming Impacts:
- Continued reduced lanes along University Boulevard East
- Temporary road and intersection closures along the University Boulevard East, especially the north side of the project
To receive text updates for traffic impacts, text UNIVBLVD to 888777.











