August 2026

You are here:
August 21, 2026 Update

Progress:Phases 1 – 6 work areas are substantially complete. Utility work in the Phase 7 and Phase 8 work areas is substantially complete. Next Steps:Sidewalk, bay parking and roadway work in the Phase 7 and Phase 8 work areas will continue. Landscaping work on the east side of Greensboro Avenue is scheduled to begin during the week…

Read article
August 14, 2026 Update

Progress: Phase 1, Phase 2, Phase 3, Phase 4, Phase 5 and Phase 6 work areas are substantially complete. The southbound lane, sidewalk and adjacent bay parking of Greensboro Avenue in the Phase 5 and Phase 6 work areas was reopened on Monday, August 10. Storm drainage in the Phase 7 and Phase 8 work areas…

Read article
August 2026 Update

Progress to Date:Crews have made steady progress upgrading utilities and preparing the corridor for upcoming construction phases. The new 12-inch water main is fully installed along with connections to the existing system. Electrical teams continued placing underground conduit, light pole bases, in-ground boxes and fiberglass equipment bases along the south side of University Boulevard East.…

Read article
August 7, 2026 Update

Progress:Phase 1, Phase 2, Phase 3 and Phase 4 work areas are substantially complete. Demolition and utility work in the Phase 5 and Phase 6 work areas are complete. Sidewalk and roadway work in the Phase 5 and Phase 6 areas are nearing completion.  Next Steps:The southbound lanes, sidewalk, and adjacent bay parking of Greensboro Avenue in the…

Read article