June 12, 2026 Update

Progress: 

The Phase 1 and Phase 2 work areas have reached substantial completion. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5.

Next Steps: 

  • Demolition, utility and new sidewalk work will continue in Phase 3 and Phase 4
  • Gas relocation will continue in Phase 7 and Phase 8 work areas

Upcoming impacts: 

  • Northbound lanes of Greensboro Avenue between 7th Street and Gary Fitts Street are closed within the Phases 3-4 work areas
  • The sidewalk corridor along the east side of Greensboro will remain open between 7th Street and Gary Fitts Street with shifts as work continues at building entrances
  • The sidewalk south of The Trunk is currently closed between The Trunk and 7th Street adjacent to the vacant buildings 
  • The northeast quadrant of the Greensboro and 7th Street intersection will be closed for approximately two weeks beginning on Monday, June 15
  • The westernmost southbound lane and adjacent parking between Gary Fitts Street and 7th Street will be closed due to gas relocation in Phase 7 and Phase 8 work areas

Pedestrian and local business access will remain open during the duration of the project.

For more information, visit tuscaloosaroads.com/Greensboro