February 5, 2024

Progress Work has begun south of SR-297 (Bryant Bridge) and continues between SR-297 and North River. A substantial portion of the cut and fill is complete on the new portion of the road between North River and Oak Glen. Construction is in process of the roadway bridge over North River, and the truss span of the…

Read article
January 11, 2024

Progress The contractor has moved 60% of the required material on the project, installed girders on 3 of the 7 spans for the vehicle bridge, and laid asphalt on around 2000 feet of new roadway.  Currently, blasting and earthwork continues between SR-297 and North River and in the new section of the roadway south of…

Read article