June 18, 2026 Update

Progress:  The Phase 1 and Phase 2 work areas are substantially complete. The northbound lane of Greensboro Avenue, the adjacent bay parking and the sidewalk between Gary Fitts Street and University Boulevard were reopened during the evening of Friday, June 5. Next Steps:  Upcoming impacts:  Pedestrian and local business access will remain open during the…