Monthly Update April 2026

Progress to date:  Over the past month, crews continued installing sewer and storm water drains and pipes along the northern sections. Additionally, utility crews continued to install gas and relocating transmission poles.  Over the Spring Break closure, the underground work that crosses University Boulevard East was completed. Next Steps:  Upcoming Impacts:  To receive text updates for…

Read article
March 2026 Monthy Update
Monthly Update March 2026

Progress:  This month, crews continued installing sanitary sewer lines and storm drains in multiple locations. Utility teams also began to install gas service lines and duct banks, while progress was completed on a manhole installation.  Next Steps:  Upcoming Impacts:  To receive text updates for traffic impacts, text UNIVBLVD to 888777.

Read article
Road Construction
Monthly Update February 2026

Progress: Stage 1 of construction began with new traffic patterns, lane, and road closures between 30th Avenue East and 34th Avenue. The site of a future drainage basin east of Windsor Drive has been mobilized and cleared. With the coordination of private utility companies,  existing locations have been marked and utility work (including sewer, gas service lines,…

Read article
Ribbon Cutting for McWright's Ferry Road
City of Tuscaloosa Holds Ribbon Cutting for McWright’s Ferry Road

The City of Tuscaloosa held a ribbon cutting ceremony for the new McWright’s Ferry Road on Friday, September 19 at 9 a.m. Tuscaloosa Mayor Walt Maddox, Judge Rob Robertson, Representative Bill Lamb, Representative Chris England, Mr. Joe Robinson and Judge Hardy McCollum spoke during the ceremony. “Today marks a monumental day for Tuscaloosa,” Mayor Walt…

Read article
Arielview of MWFR
August 1, 2025

Progress The McWright’s Ferry Road project has reached another significant milestone.  The final asphalt surface has been placed, and temporary striping has been completed on Rice Mine Road and SR-297, McWright’s Ferry Road, and on New Watermelon Road.  This marks completion of one of the last major phases of construction.  The newly completed intersection at…

Read article
Arielview. of MWFRP
June 1, 2025

Progress Remaining grading, stone base placement, and lower layers of pavement were completed on the north end of the project from Sierra Dr to New Watermelon marking another milestone on the project.  The footprint of McWright’s Ferry Road has reached the northern-most point on the project as it ties into New Watermelon Road.  This portion…

Read article
Ariel view of MWFR
March 1, 2025

Progress Paving is complete on the right turn lanes at the Rice Mine Road and SR-297 (Bryant Bridge) intersection. Additional paving is in process to complete the access in front of Coral Industries. The contractor has focused on constructing the McWright’s Ferry Road tie-in outside existing travel lanes, and on additional widening of existing McWright’s Ferry Road between…

Read article