Weekly Update May 8th
Progress: Construction began on Monday May 4. Traffic control, wayfinding signage, and construction fencing was installed. Demolition began in the Phase 1 work area, along with storm drainage, concrete curb, gutter and sidewalk installation. Spire has begun gas relocation. Next Steps: In the Phase 1 work area storm drainage, concrete curb, gutter and sidewalk/bay parking…