Monthly Update March 2026
Progress: This month, crews continued installing sanitary sewer lines and storm drains in multiple locations. Utility teams also began to install gas service lines and duct banks, while progress was completed on a manhole installation. Next Steps: Upcoming Impacts: To receive text updates for traffic impacts, text UNIVBLVD to 888777.