May 1, 2024

You are here:
May 1, 2024 

Progress Grading is almost complete! Only three areas of earthwork involving blasting and mass hauling remain. In April, the focus shifted to complete installation of around 3,800 feet of waterline on McWright’s Ferry Road. An additional crew was assigned to this effort, taking the completion time from the projection of a couple of months down…

Read article