Progress Drilling, blasting, and excavation continue to be the primary focus of the project. The contractor is nearing the end of the large-scale earthmoving, and the majority of the rock has been moved. The roadway is on grade between SR-297 (Bryant Bridge) and North River. Grading and earthwork south of SR-297 are progressing as well. The new…