January 11, 2024
Progress The contractor has moved 60% of the required material on the project, installed girders on 3 of the 7 spans for the vehicle bridge, and laid asphalt on around 2000 feet of new roadway. Currently, blasting and earthwork continues between SR-297 and North River and in the new section of the roadway south of…
Read article